SteadyWeeks Free 8-week checkFree check

How to work out your trade team's capacity in hours

A simple formula for the hours your team can really sell each week, a worked example, and the things most owners forget to take off.

The short answer

Your weekly capacity is your field staff multiplied by their usual weekly hours, minus time away (leave, RDOs, TAFE days, public holidays), minus time spent off the tools (quoting, admin, meetings, and travel if your job times don't already include it). For six techs on 38 hours that's 228 hours on paper, and often closer to 150 hours you can actually sell.

The formula

Paid hoursField staff × usual weekly hours
Time awayLeave, RDOs, TAFE days, public holidays
Time off the toolsQuoting, admin, meetings, stock runs
CapacityThe hours you can sell that week

Count the people who do billable work in the field, and multiply by the hours each one usually works in a week. Six techs on a 38-hour week is 228 hours.

Count apprentices at the hours they're on site. If you, the owner, spend two days a week on the tools, count two days, not five.

Step 2: Take off time away

For the week you're looking at, take off:

  • Annual and personal leave you already know about, even if it isn't in the diary yet.
  • RDOs, if your team works on a rostered day off arrangement.
  • TAFE days for apprentices.
  • Public holidays, at the hours each person would normally have worked that day. Public holidays differ between states, so use your own state's list.

Step 3: Take off time off the tools

Not every working hour can be sold. Quoting visits, admin, toolbox meetings, stock runs and vehicle time all come out of the week. The easiest way to find your number is to look at one normal week and add up the hours that weren't on a job.

One thing to watch: if the job times you use already include travel, as ours do, don't take travel off again here. Count it once.

A worked example

Example: six techs, one week
LineHours
6 techs × 38 hours228
One tech on annual leave all week− 38
Apprentice at TAFE on Tuesday− 7.6
One RDO on Friday− 7.6
Hours on site174.8
Quoting, admin and meetings, about 15%− 26.2
Capacity you can sell148.6

Made-up example. The 15% is only for illustration; measure your own.

That's a third less than the 228 hours on paper, and it's why a week that looks two-thirds full can turn out to be completely full.

What to do with the number

Capacity on its own doesn't tell you much. Compare it with the hours already committed for that week: booked jobs, jobs you've won but haven't booked, and a share of your open quotes. Then read the week with four simple bands:

  • Under 65%: room. Fill it now with quotes, follow-ups and marketing.
  • 65 to 90%: steady. Keep going.
  • 90 to 100%: tight. Be careful taking on big jobs.
  • Over 100%: over. Move a job, add overtime or push a start date.

Our guide to planning eight weeks ahead in ServiceM8 shows how to count the committed side, including won jobs and quotes.

Common mistakes

  1. Counting the owner as a full-time tech when half the week goes on quotes and the phone.
  2. Waiting for leave to be entered before counting it. If you know about it, take it off.
  3. Forgetting TAFE blocks, which often fall in the same weeks for several apprentices.
  4. Using another state's public holidays, or forgetting the ones that fall on a weekday in the middle of a busy month.
  5. Taking travel off twice, once in capacity and once in job times.

Questions

How do I calculate my team's capacity in hours?

Multiply your field staff by their usual weekly hours, then take off leave, RDOs, TAFE days and public holidays. Then take off the time that isn't on the tools, such as travel between jobs, quoting and admin. What's left is the hours you can actually sell.

What is a good utilisation rate for a trade business?

There's no single right number. A useful way to read it: under 65% of your hours committed is room to fill, 65 to 90% is steady, 90 to 100% is tight, and over 100% means something has to move.

What is a labour table?

A labour table lists your common job types and how long each one really takes, including travel. It turns a count of jobs and quotes into hours, so you can compare them with the hours your team has.

Rather not work this out every week?

SteadyWeeks does this for each of the next eight weeks from your ServiceM8 data, including leave and public holidays, and emails you every Monday.

Get my free 8-week check